- sunk cost – cost already
incurred in the past and cannot be recovered, do not consider
anymore
- opportunity cost –
difference in value between one path vs alternative (= 100% of
value of next best alternative)
- value analysis/
engineering – cost reduction without affecting the scope
- Benefit Cost Analysis
(BCA) / Cost Benefit Analysis (CBA) – determine feasibility, bigger
benefit/cost ratio (BCR)
- Payback Period – the
length of time to recover the investment
- Return on Investment
(ROI) – the efficiency of investment = (Gain-Cost)/Cost
- Time Value of Money –
Present Value (PV) = value / (1+interest rate)*year, Future Value
(FV) = value * (1+interest rate)*year
- Net Present Value (NPV)
= PV of cash inflows – PV of cash outflows (cost)
- funding for project:
self-fund, funding with equity, funding with debts
- discount rate
- rate used to calculate present value of expected yearly benefits
and costs
Project Cost
Management PITTOs:
Processes
|
Inputs
|
Tools & Techniques
|
Output
|
Plan Cost Management
|
Project Management Plan
Project Charter Enterprise Environment Factors Organization Process Assets |
Expert Judgment
Analytical Techniques Meetings |
Cost
Management Plan
|
Estimate Costs
|
Cost Management Plan
Human Resource Management Plan Scope Baseline Project Schedule Risk Register Enterprise Environment Factors Organization Process Assets |
Expert Judgment
Analogous Estimating Parametric Estimating Three Point Estimates Reserve Analysis Cost of Quality Project Management Software Vendor Bid Analysis Group Decision Making Techniques |
Activity
Cost Estimates
Basis of Estimates Project Document Updates |
Determine Budget
|
Cost Management Plan
Scope Baseline Activity Cost Estimates Basis of Estimates Project Schedule Resource Calendars Risk Register Agreements Organization Process Assets |
Cost Aggregation
Reserve Analysis Historical Relationships Funding Limit Reconciliation Expert Judgment |
Cost
Baseline
Project Funding Requirements Project Document Updates |
Control Costs
|
Project Management Plan
Project Funding Requirements Work Performance Data Organization Process Assets |
Earned
Value Management
Forecasting To Complete Performance Index (TCPI) Performance Reviews Project Management Software Reserve Analysis |
Cost
Forecasts
Change Requests Work Performance Info Organization Process Assets Updates PM Plan Updates Project Document Updates |
Plan
Cost Management
- The Cost Management
Plan establishes: i) level of accuracy and level of precision,
ii) unit of measurement, iii) WBS procedure links (to control account
(CA)), iv) control threshold, v) earned value rules of performance,
reporting, funding and processes
- Life cycle costing = total
cost of ownership : production cost, running and maintenance
cost, etc.
Estimate
Costs
- similar to Estimate
Activity Resources
- look for ways to reduce
cost
- ensure the SME to
deliver the estimates (more accurate)
- based on WBS
- Cost Types
- Variable costs -
costs change with the amount of work, e.g. hourly consultants
- Fixed costs - costs
that are constant, e.g. equipment leases
- Direct costs – directly
attributed to the project
- Indirect costs – shared costs
like AC, lighting, etc.
- Cost Estimate Tools
- Analogous Estimating (Top Down
Estimate) – compare to a similar project in the past (an estimating
heuristic/rule of thumb)
- Parametric Estimating – use a
parameter and repetitive units of identical work
- Bottom-up Estimating – detailed
estimates of each individual activity from historical data, more accurate
and time-consuming
- Activity Cost Estimates
may include indirect cost and contingency reserves
- usually in a range
of values
- Basis of
Estimates - detailed analysis on how the cost
estimate was derived (assumptions, constraints, possible range (+/-15%),
confidence level of final estimate)
Determine
Budget
- Budget is more about when to
spend money
- Historical
Relationships - analogous/parametric estimation
- Reserve Analysis – addresses Management
Reserve (unknown unknowns) and Contingency Reserve (known
risks) [not included in calculation of earned value management]
- Funding Limit
Reconciliation – addresses variance between funding
limit (e.g. monthly or yearly limit) and planned expenditure, may require rescheduling
of work to level of the rate of expenditure
- Value Engineering – to improve quality/shorten
schedule without affecting the scope
- Project Budget = Cost
baseline (the approved time-phased budget) + Management
Reserve
- when management reserve
is used during project execution, the amount is added to the
cost baseline
- S-curve : total project expenditure
over project lifecycle
Control
Costs
- Check against the Project
Funding Requirements
- including informing
stakeholders of all approved changes and their costs
- Earned Value
Calculation
- Index > 1: under
budget/ahead of schedule
- Index < 1: over budget/behind
schedule
- Estimate at Complete:
1) new estimate required (original flawed), 2) no BAC variance, 3) CPI
will continue, 4) sub-standard cost/schedule will continue
- TCPI: >1 not
enough funding remain (over budget), <1 more fund
available than needed (under budget)
- Earned Value Accrual
- Discrete Efforts – describes
activities that can be planned/measured for output, including Fixed
Formula (activity given a % of budget of work package at start
and earn the remaining when completed, e.g. 50/50, 20/80 or 0/100), Weighted
Milestone (earn value for milestones of deliverables of the work
package), Percentage Complete, Physical Measurement
- Apportioned Efforts – describes work that
has a direct/supporting relationship to discrete work, e.g. testing, pm
activities, calculated as % of the discrete work
- Level of Efforts (LOE) – describes
activities without deliverables, e.g. troubleshooting, assigned the
earned value as scheduled, without schedule variance but may have
cost variance
- e.g. perform Control
Cost weekly during execution where money is spent fastest
- Variance Analysis – to
check against the baseline for any variance
- SPI at end of project
must be 1
- SPI is NOT telling much
information to whether the project is on schedule as the Critical Path
must also be investigated to get a meaningful picture
No comments:
Post a Comment
Be the first to comment..