Sunday, May 25, 2014

15) PMP Formulas and Calculation

PMP Formulas and Calculation for the Certification Demystified

Many consider the most difficult part of the PMP exam to be the calculations and PMP formulas. Luckily PMP calculation is not quantum physics, you just need to understand and memorize the following PMP Calculation formulas.


PMP Formulas
Name (Abbreviation)
Formula
Interpretation
No. of Communication Channels
n (n-1)/2
n = number of members in the team
n should include the project manager

e.g. if the no. of team members increase from 4 to 5, the increase in communication channels:
5(5-1)/2 – 4(4-1)/2 = 4
Schedule Performance Index (SPI)
SPI = EV/PV
EV = Earned Value
PV = Planned Value
< 1    behind schedule
= 1    on schedule
> 1    ahead of schedule
Cost Performance Index (CPI)
CPI = EV/AC
EV = Earned Value
AC = Actual Cost
< 1    Over budget
= 1    On budget
> 1    Under budget

sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment
Schedule Variance (SV)
SV = EV – PV
EV = Earned Value
PV = Planned Value
< 0    Behind schedule
= 0    On schedule
> 0    Ahead of schedule
Cost Variance (CV)
CV = EV – AC
EV = Earned Value
AC = Actual Cost
< 0    Over budget
= 0    On budget
> 0    Under Budget
Estimate at Completion (EAC) if original is flawed
EAC = AC + New ETC
AC = Actual Cost
New ETC = New Estimate to Completion
if the original estimate is based on wrong data/assumptions or circumstances have changed
Estimate at Completion (EAC) if BAC remains the same
EAC = AC + BAC – EV
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
the variance is caused by a one-time event and is not likely to happen again
Estimate at Completion (EAC) if CPI remains the same
EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index
if the CPI would remain the same till end of project, i.e. the original estimation is not accurate
Estimate at Completion (EAC) if substandard performance continues
EAC = AC + (BAC -EV)/(CPI*SPI)
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used
To-Complete Performance Index (TCPI)
TCPI = (BAC – EV)/
(BAC – AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost
TCPI = Remaining Work
/Remaining Funds
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
< 1    Under budget
= 1    On budget
> 1    Over budget
Estimate to Completion 
ETC = EAC -AC
EAC = Estimate at Completion
AC = Actual Cost
Variance at Completion
VAC = BAC – EAC
BAC = Budget at completion
EAC = Estimate at Completion
< 0    Under budget
= 0    On budget
> 0    Over budget
PERT Estimation
(O + 4M + P)/6
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
Standard Deviation
(P – O)/6
O= Optimistic estimate
P= Pessimistic estimate
this is a rough estimate for the standard deviation
Float/Slack
LS – ES
LS = Late start
ES = Early start
LF – EF
LF = Late finish
EF = Early finish
= 0    On critical path
< 0    Behind

Hope, the series of my blogs in PMI - PMP (PMBOK 5)  is informative and useful inputs for your exam if you are preparing for PMP Certificate. All the very best!

No comments:

Post a Comment

Be the first to comment..