PMP Formulas and Calculation for the Certification
Demystified
Many consider the most difficult part of the PMP exam to be the calculations and PMP formulas. Luckily PMP calculation is not quantum physics, you just need to understand and memorize the following PMP Calculation formulas.
Many consider the most difficult part of the PMP exam to be the calculations and PMP formulas. Luckily PMP calculation is not quantum physics, you just need to understand and memorize the following PMP Calculation formulas.
PMP
Formulas
|
||
Name (Abbreviation)
|
Formula
|
Interpretation
|
No. of Communication Channels
|
n (n-1)/2
n = number of members in
the team
|
n should include the project
manager
e.g. if the no. of team members increase from 4 to 5, the increase in communication channels: 5(5-1)/2 – 4(4-1)/2 = 4 |
Schedule
Performance Index (SPI)
|
SPI = EV/PV
EV = Earned
Value
PV = Planned Value |
< 1 behind schedule
= 1 on schedule > 1 ahead of schedule |
Cost
Performance Index (CPI)
|
CPI = EV/AC
EV = Earned
Value
AC = Actual Cost |
< 1 Over budget
= 1 On budget > 1 Under budget sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment |
Schedule
Variance (SV)
|
SV = EV – PV
EV = Earned
Value
PV = Planned Value |
< 0 Behind schedule
= 0 On schedule > 0 Ahead of schedule |
Cost
Variance (CV)
|
CV = EV – AC
EV = Earned
Value
AC = Actual Cost |
< 0 Over budget
= 0 On budget > 0 Under Budget |
Estimate at
Completion (EAC) if original is flawed
|
EAC = AC + New ETC
AC
= Actual Cost
New ETC = New Estimate to Completion |
if the original estimate is
based on wrong data/assumptions or circumstances have changed
|
Estimate at
Completion (EAC) if BAC remains the same
|
EAC = AC + BAC – EV
AC
= Actual Cost
BAC = Budget at completion EV = Earned Value |
the variance is caused by a
one-time event and is not likely to happen again
|
Estimate at
Completion (EAC) if CPI remains the same
|
EAC = BAC/CPI
BAC = Budget
at completion
CPI = Cost performance index |
if the CPI would remain the
same till end of project, i.e. the original estimation is not accurate
|
Estimate at
Completion (EAC) if substandard performance continues
|
EAC = AC + (BAC
-EV)/(CPI*SPI)
AC
= Actual Cost
BAC = Budget at completion EV = Earned Value CPI = Cost Performance Index SPI = Schedule Performance Index |
use when the
question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this
formula is not likely to be used
|
To-Complete
Performance Index (TCPI)
|
TCPI = (BAC – EV)/
(BAC – AC)
BAC = Budget
at completion
EV = Earned value AC = Actual Cost
TCPI = Remaining Work
/Remaining Funds
BAC = Budget
at completion
EV = Earned value CPI = Cost performance index |
< 1 Under budget
= 1 On budget > 1 Over budget |
Estimate to
Completion
|
ETC = EAC -AC
EAC =
Estimate at Completion
AC = Actual Cost |
|
Variance at
Completion
|
VAC = BAC – EAC
BAC = Budget
at completion
EAC = Estimate at Completion |
< 0
Under budget
= 0 On budget > 0 Over budget |
PERT Estimation
|
(O + 4M +
P)/6
O=
Optimistic estimate
M= Most Likely estimate P= Pessimistic estimate |
|
Standard
Deviation
|
(P – O)/6
O=
Optimistic estimate
P= Pessimistic estimate |
this is a rough estimate for
the standard deviation
|
Float/Slack
|
LS – ES
LS = Late
start
ES = Early start
LF – EF
LF = Late
finish
EF = Early finish |
= 0
On critical path
< 0 Behind |
Hope, the series of my blogs in PMI - PMP (PMBOK 5) is informative and useful inputs for your exam if you are preparing for PMP Certificate. All the very best!
No comments:
Post a Comment
Be the first to comment..